Most Project Managers use the terms ‘Fast-tracking’ and ‘Crashing the Schedule’ interchangeably. And that’s fine. But, strictly, they are different.
🎓 Learn Project Management with Mike:
The Project Manager's Skills Mastery Program
https://school.onlinepmcourses.com/p/...
Crashing a Project – or Crashing a Timeline – is the use of additional resources to get things done more quickly.
Fast-tracking is the practice of doing work in parallel, that you would normally do sequentially.
Recommended Videos
Carefully curated video recommendations for you:
🎬 How to Create a Project Schedule - 21 Steps in 5 Stages
• How to Create a Project Schedule - 21...
🎬 What is Resource Levelling? And how does it differ from Resource Smoothing?
• What is Resource Levelling? And how d...
🎬 How to Deduce Project Resource Requirements
• How to Deduce Project Resource Requir...
🎒 A while back, I asked Project Managers in a couple of forums what material things you need to have, to do your job as a Project Manager. They responded magnificently. I compiled their answers into a Kit list.
https://kit.co/MikeClayton/what-a-pro...
Note that the links are affiliated.
🎬 For more great Project Management videos, please subscribe to this channel: / @onlinepmcourses
🎁 For all our great Project Management articles and resources, please check out the OnlinePMCourses website: https://onlinepmcourses.com/
🏛 For basic Management Courses - free training hosted on YouTube, with 2 new management lessons a week, check out our sister channel, Management Courses: / managementcourses
🎓 For more of our Project Management videos in themed collections, join our Free Academy of Project Management: https://onlinepmcourses.com/free-acad...
⏱ Chapter Markers...
00:00 - Fast-tracking and crashing the schedule
00:19 - Two schedule compression techniques
01:14 - Crashing
01:42 - Fast-tracking
03:01 - Summary: Comparing Fast-tracking with Crashing
#ScheduleCompression #ProjectManagement #FastTracking